Agriculture uses and development
View the lodgment criteria, submission documents, and process for agriculture uses and development.
Applicability and Criteria
For new erection, reconstruction, additions & alteration works, and change of use of Agriculture development on land leased by the State or a statutory body for Agriculture use that can meet the criteria.
Who can submit?
For New Erection and Additions & Alterations Works: Qualified Person (registered architect or engineer)
For Change of Use: Business owner, landlord, consultant or a Qualified Person
Type of Development allowed
Agriculture development on land leased by the State or a statutory body for Agriculture use.
Lodgment fee
For New Erection/Reconstruction: $1200
For Additions & Alterations Works: $850
For Change of Use: $150
How to lodge?
From 1 Oct 2025, lodgement application for all new projects with Gross Floor Area (GFA) of 30,000m2 and above must be submitted via CORENET X. You may visit the CORENET X Portal to make your submission.
New projects with a GFA below 30,000m2 may continue to be submitted via CORENET 2. To do so, please complete and lodge the plans through CORENET 2, using EDA form and accompanied by the various documents as stipulated in the "Documents to be submitted" section above.
After plan is lodged
An acknowledgement letter will be issued by URA.
If the lodgment application is made under CORENET 2, please proceed to apply for approval from Building & Construction Authority (BCA) if BCA’s approval is required.
The authorisation is valid for two years from the date of the acknowledgement letter. If works are not completed within the two years validity period, you may apply for extension of the lodgment authorisation (up to two times). After which, a fresh lodgment is to be made.
Legislation
You are required to comply with the provisions of the Planning (Development of Land for Agriculture Use – Lodgment Authorisation) Notification.
Development Control Guidelines
Table 1: Development control guidelines
Aspect | Guideline | ||
Minimum Building Setback |
| ||
Minimum Road Buffer | Road Category | Minimum Width of Buffer | Specification of Buffer |
Category 1 – Expressway | 15m | 5m green, 10m physical | |
Category 2 – Major Arterial A | 7.5m | 3m green, 4.5m physical | |
Category 3 – Major Arterial B | 5m | 3m green, 2m physical | |
Category 4 & 5 – Other major roads, minor roads, and slip roads | 5m | 3m green, 2m physical | |
Floor-to-floor Height | No control | ||
Building Height | Prevailing height controls apply (including height controls for Lim Chu Kang [PDF, 713.12 KB]) | ||
Permissible Uses |
| ||
Non-Permissible Uses |
| ||
Earthworks |
| ||
Boundary and Retaining Walls |
| ||
Lodgment Criteria
The proposal must satisfy the following criteria:
Land is leased by the State or a statutory body for Agriculture development*
Does not encroach onto any other land
Development plot abuts a public road allowing direct vehicular access
Complies with all Development Control guidelines stated above
Compliance with the prevailing building heights

Lim Chu Kang Height Control Plan
Earthfill works on the land, if any, will not cause the level of any point in the land to be more than 1.5 metres above the lower of the following:
the level of that point in the land at the time when the land was leased or agreed to be leased by the State or statutory body; or
the level of any point at the abutting edge of abutting land
Does not have any unauthorised works
Endorsed by the lessor for the land (e.g. SLA, SFA, NParks)
Obtained the consent from owner of the land
Obtain clearances from all relevant technical departments directly, including LTA, NParks, FSSD, PUB, NEA, DSTA and BCA
* Except for works within the boundary as shown here [PDF, 477 KB], which will require a Development Application to be submitted.