Building Setback from Boundary
Check the guidelines relating to building setback for places of worship

Setback Requirements
All PWs shall be sufficiently set back from the road and common boundary. The setback distance is measured from the road reserve1 line or boundary line to the external wall of the buildings, excluding land to be vested to the State for road or drainage or public purpose.
All PWs fronting a public road shall provide a road buffer, the width of which depends on the hierarchy of the road. A green buffer shall be set aside in the road buffer depending on the width of the road buffer.
The buffer requirements for the Road Categories 1 to 5 are in Table 1 below. The common boundary setback requirements are in Table 2 below. Different setback requirements may apply for sites within the Geylang area or the Central Area, both of which are guided by Urban Design guidelines.
1 Road Reserve: The plot of land to be vested in the State as required under the Street Works Act. It is demarcated by the line of Road Reserve in the Road Line Plan and the site boundary.
Road Buffer and Green Buffer
Table 1: Road Buffer and Green Buffer
Road Category | Road Buffer |
|---|---|
Category 1 | 15m |
Category 2 | 7.5m |
Category 3 | 5m |
Category 4 - 5 and slip road | 5m |
Common Boundary Setback and Peripheral Planting Verge
Table 2: Common Boundary Setback and Peripheral Planting Verge
Type of Boundary | Building Setback Requirement |
|---|---|
Common boundary with other developments | Minimum 4.5m |
Common boundary with an industrial development | No setback (see note below) is required at the common boundary between an industrial development and a Place of Worship (PW) development subject to the following conditions:
Note: Where the building is proposed to abut the common boundary, the applicant should put in place systems/measures to facilitate down-stream building maintenance at the common boundary. |
Setback for Building Appendages
Table 3: Setback for Building Appendages
Building Feature | Within Road Buffer | Within Setback from Common Boundaries |
|---|---|---|
Roof eaves | Allowed, provided it is not within the green buffer | Allowed, provided it is not within the 2.0m peripheral planting verge |
Sun-shading devices & RC ledges (cantilevered) |